Building the GEK Gasifier in seven parts

Step 19Downdraft reactor - 4

Downdraft reactor - 4
Outer Vessel: Weld top flange ring onto outer reactor vessel tube.

  • Orientation: Use any tab and slot position, but make sure flange is flush with top of vessel tube
  • Tab and Slot start position: The "center" of the slot at the vessel seam is 3/16" from the material edge. This results in a 1/4" space between the edge of the tab and slot on the material side of the slot.
  • Pull vessel tube and flange tight together with C clamps as you tack around the circle
  • Weld ONLY on the underside. No welding on the joint side of the flange
  • Grind top surface flat after welding
  • Clean up flange holes with a 11/32" drill
« Previous StepDownload PDFView All StepsNext Step »

Pro

Get More Out of Instructables

Already have an Account?

close

All Steps Viewing
View all steps of an Instructable on the same page when you're a Pro Member.

Upgrade to Pro today!
114
Followers
3
Author:jimmason